Start of the 2025-2026 School Year
-
Graded the back fire road in preparation for asphalt placement.
-
Installed concrete footings for the Learning Commons.
-
Completed underground electrical and plumbing rough-ins for the slabs.
-
Prepared the basement slab for the concrete pour of the Learning Commons foundation.
-
Finished small projects at the playground.
-
Poured the concrete sidewalk on the outside of the playground.
-
Placed prayer tags under the foundation of the Learning Commons and spent time praying over the building project and the future ministry of the students who will serve and grow there.
%20(1).png)
End of May 2025
Big changes ahead! The retaining wall for the new Gold Playground goes up, and dirt starts moving to prep the site for the Learning Commons.
Renovations to Building 300 begin.
End of February 2025
Administration is packing up and moving to the old Lower School! Here’s a map to help you find everyone in their new spaces.
We officially broke ground on the Learning Commons! Check out the photos from a special morning celebrating God’s faithfulness to Whitefield Academy through the years.
Mid-February 2025
We’re packing up Building 100 and getting ready for a big move! The Campus Store and our security team will soon settle into their new home in the old Lower School. Exciting changes ahead!
Summer 2025
Much of the work on the Learning Commons this summer took place underground, with a focus on utilities and site grading. Here is an overview of what was accomplished:
-
Georgia Power completely rewired the campus with a new loop of power lines. This improvement is expected to help resolve past power issues and reduce surges.
-
The gas meter that once sat prominently in front of the campus store was relocated so it no longer obstructs the view of the Learning Commons. During the week without gas, we were especially grateful to Christina Dolby and her Sage team for creatively providing lunches for summer camp in other ways.
-
The retaining wall was completed for both the relocated gold playground and the new parking spaces behind the Learning Commons.
-
The Learning Commons foundation wall footings, wall forms, and concrete pours were finished.
-
Building 300 was outfitted with interior spaces and ramps to prepare for the relocation of Lower School Arts, Lower School Science, and the Lower School Cottage Conference Room before the start of school.
-
Move-in day to Building 300 took place, and Lower School Arts, Lower School Science, and the Lower School Cottage Conference Room are now settled into their new spaces.
-
The gold playground was reinstalled in its new location with a pour-in-place rubber surface. Thanks to additional campaign gifts, this new playground location also features shade structures.
End of May 2025
Big changes ahead! The retaining wall for the new Gold Playground goes up, and dirt starts moving to prep the site for the Learning Commons.
Renovations to Building 300 begin.
End of February 2025
Administration is packing up and moving to the old Lower School! Here’s a map to help you find everyone in their new spaces.
We officially broke ground on the Learning Commons! Check out the photos from a special morning celebrating God’s faithfulness to Whitefield Academy through the years.
Mid-February 2025
We’re packing up Building 100 and getting ready for a big move! The Campus Store and our security team will soon settle into their new home in the old Lower School. Exciting changes ahead!
End of May 2025
Big changes ahead! The retaining wall for the new Gold Playground goes up, and dirt starts moving to prep the site for the Learning Commons.
Renovations to Building 300 begin.
End of February 2025
Administration is packing up and moving to the old Lower School! Here’s a map to help you find everyone in their new spaces.
We officially broke ground on the Learning Commons! Check out the photos from a special morning celebrating God’s faithfulness to Whitefield Academy through the years.
Mid-February 2025
We’re packing up Building 100 and getting ready for a big move! The Campus Store and our security team will soon settle into their new home in the old Lower School. Exciting changes ahead!
Mid-April 2025
-
Time for a move — Building 300 will be relocated.
-
Tree trimming behind the fire lane—seems like a small step, but watching the machine clip a massive tree, hold it gently in its claw, and lay it down with precision? Kind of amazing!
March 2025
-
Demolition begins! They’ll start with Building 100 (formerly the Campus Store) and work their way down the line.

End of February 2025
Administration is packing up and moving to the old Lower School!
Here’s a map to help you find everyone in their new spaces.

We officially broke ground on the Learning Commons! Check out the photos from a special morning celebrating God’s faithfulness to Whitefield Academy through the years.